Latest Updates — London
UPDATED
🏙️ London TfL’s renewals backlog has reached £6.5bn, with 42% of track classed ‘very poor’; passengers are losing over 800,000 hours a week to deteriorating assets (London Assembly Budget and Performance Committee, 21 Oct 2026). West London Orbital will not be extended beyond Hounslow, the Mayor said (MyLondon, 16 Oct 2026).
Northern Ireland — DrumcreeDrumcree stand-off: the parade was banned on 9 Oct 2026 after 13 days. Justice Minister Naomi Long told the Assembly the policing cost is now estimated at £5.5m (19 Oct 2026). See the NI dashboard.→ Northern Ireland — A5 ruling, 6 Oct 2026A5 Western Transport Corridor: the Court of Appeal in Belfast today allowed DfI’s appeal on all grounds, lifting the legal block on the first phase (ITV News; Irish Times; Belfast Live, 6 Oct 2026). The Alternative A5 Alliance can still seek permission to appeal to the UK Supreme Court; no application has been reported. Cost of delay: had it gone ahead as planned in 2012 (completion 2018), the approved business case was £799m (£975m at 2017 prices); it is now £2.1bn (DfI, Oct 2024) — roughly £1.1bn–£1.3bn more to be borne, plus £192.5m already spent with no road built (NIAO 2019; DfI, Sep 2026). For the families of the more than 50 people killed on the A5 since 2006 (ITV News; BBC), it is a day when their prayers were in some way answered — CPD hopes no further lives are lost while the scheme moves forward, with Climate Change Act compliance remaining an important factor. No construction start date yet.→
In memory of the 58 people who have lost their lives on the A5 since 2007 (Donegal News, 3 Nov 2026) — A5 Enough is Enough
Construction costs — 10-year check, 2016 to 2026Has building nearly doubled in cost in ten years? In Ireland, almost: commercial tender prices rose 83% from the first half of 2016 to the first half of 2026 (SCSI Tender Price Index, Aug 2026). In Great Britain the rise is closer to half than double: prices paid for new construction work rose 47% from June 2016 to June 2026 — housing 55%, infrastructure 44%, public buildings 41% (ONS construction output price indices, Aug 2026). Building materials rose faster, 68% from the 2016 average to August 2026 (DBT, provisional), against 42% for general prices over the same ten years (ONS CPI). No official Northern Ireland-only price index exists: NISRA price-adjusts NI construction output using these ONS indices because “regional OPIs are not available” (NISRA construction methodology report, Dec 2025). Construction has outpaced general inflation, so every year a scheme drifts it is re-priced in a dearer market.Non-official comparison — not an official statisticRider Levett Bucknall, a private consultancy, forecasts Northern Ireland tender prices to rise 3% in 2026 and 3.25% a year in 2027, 2028 and 2029 — about 13% over the four years if compounded (CPD calculation). RLB names labour as “the most significant driver of construction inflation” in NI. This is a commercial forecast, not a measured 10-year change (RLB Construction Market Intelligence, Northern Ireland, Q3 2026).
🌍All jurisdictionsOpen the British Isles & Australia hub for updates across all seven jurisdictions, the separate per-currency overrun clocks and the reconciliation panel.→
ExtendIQ SiteIQ NI
LATEST
Delays19 of 40 schemes in Significant Delay · 5 Minor Delay · 6 Not Started · 3 Paused · 6 On Track · 1 Cancelled● Cost Clock£363.24/sec — London overrun clock running since 30 Apr 2026 — base overrun £149.023bn● Crossrail 2Crossrail 2: Shelved — TfL and Government paused indefinitely — tens of millions in pre-development costs written off● HS2 EustonHS2 Euston Station: Significant Delay — scope reduction, cost spiral — terminus design under review● New SchemesOld Oak Common OPDC, Nine Elms–Pimlico Bridge and Heathrow Third Runway added — full 40-scheme portfolio now tracked● SilvertownSilvertown Tunnel: On Track — opens 2025 — one of few major London infrastructure schemes on schedule● ScoreCPD combined score tracked across 40 London schemes — £363.24/sec overrun accumulating● Delays19 of 40 schemes in Significant Delay · 5 Minor Delay · 6 Not Started · 3 Paused · 6 On Track · 1 Cancelled● Cost Clock£363.24/sec — London overrun clock running since 30 Apr 2026 — base overrun £149.023bn● Crossrail 2Crossrail 2: Shelved — TfL and Government paused indefinitely — tens of millions in pre-development costs written off● HS2 EustonHS2 Euston Station: Significant Delay — scope reduction, cost spiral — terminus design under review● New SchemesOld Oak Common OPDC, Nine Elms–Pimlico Bridge and Heathrow Third Runway added — full 40-scheme portfolio now tracked● SilvertownSilvertown Tunnel: On Track — opens 2025 — one of few major London infrastructure schemes on schedule● ScoreCPD combined score tracked across 40 London schemes — £363.24/sec overrun accumulating●
Total Cost Overrun — All 40 Schemes
—
% above announced cost across all schemes
Total Portfolio — Current Estimated Cost
—
Across all 40 tracked London schemes
CPD Index — London Lower score = worse delivery performance (0 = total failure, 100 = perfect)
CPD-C | Cost Performance
0
/ 100
🔴 Critical
CPD-D | Delivery Performance
0
/ 100
🟡 Concerning
CPD Combined Index
0
/ 100
🟠 Poor
Portfolio Overview

Programme Status Breakdown

Delay Distribution (Weeks)

Announced vs. Current Cost — All Schemes (£m)

Cost Escalation Forecast to 2032 — Active Schemes

Key Facts

Crossrail — 4 Years Late, £4.1bn Over Budget

Opened 24 May 2022, nearly four years after the December 2018 target. Total cost reached £18.9bn against a £14.8bn baseline — a £4.1bn overrun. Repeated signalling failures, contract disputes and COVID-19 disruption combined to produce one of Europe's most-scrutinised infrastructure delays. Full end-to-end services did not commence until May 2023.

HS2 Euston — At Least 9 Years Late, £3.4bn Over

Originally due to open to Euston in 2026. No revised date has been set for the Euston terminus. The PAC warned costs could approach £80bn for Phase 1. The station was scaled back to six platforms with private finance — a route the Public Accounts Committee expressed scepticism will materialise. Tunnel boring continues but station construction has not started.

Hammersmith Bridge — 525% Cost Explosion

Closed to motor traffic in April 2019. Initial repair estimate: £40m. Current estimate: £250m — a 525% increase. Funding disputes between LBHF, DfT and TfL remain unresolved as of 2026. The bridge risks remaining closed to vehicles until 2035, making it nearly two decades from closure to possible reopening — for a Victorian structure in one of London's most affluent boroughs.

Four Lines Modernisation — 7 Years Behind, £1.3bn Over

The 4LM digital signalling upgrade for Circle, District, Hammersmith & City and Metropolitan lines was originally due to complete around 2022. The programme budget rose to £5.541bn (from £4.2bn) by June 2024, with TfL's own Q2 2024/25 report noting the estimated final cost already exceeds even this figure. Several signalling areas remain unstarted as of 2026; realistic full completion is late 2020s.

New Hospitals Programme — £56bn Nationally

Boris Johnson's 2020 pledge of "40 new hospitals by 2030" has become a £56bn programme extending to 2045–46 — a £33.8bn increase on 2023 estimates. London schemes include Whipps Cross, Charing Cross, Hammersmith Hospital, St Mary's Paddington and Sutton SECH. Seven RAAC-risk hospitals will miss the 2030 deadline, now expected to open 2032–33.

Scheme Register 40 schemes tracked · click row for details
Sort:
Scheme Status Announced Current Est. Variance Delay ETI Stranded Detail

Methodology & Sources

CPD Index (0–100): CPD-C (Cost Performance) measures the proportion of schemes delivered at or near announced cost, with a severity penalty for overruns greater than 25%. CPD-D (Delivery Performance) measures the proportion of schemes free from significant delay, with a minor penalty for smaller slippages. The combined CPD score applies a 60/40 weighting — 60% CPD-D (Delivery) and 40% CPD-C (Cost), reflecting the judgement that delivery failure imposes compounding societal and economic costs beyond the overrun figure alone. A score of 100 indicates a perfect delivery record; 0 indicates complete systemic failure.

Clock: The live clock is computed from the scheme table on this page rather than from a stored total. It starts from the accumulated cost overrun on every scheme still live — any status other than Completed, Cancelled or Paused, with announced cost treated as zero where no published baseline exists — and then accrues construction inflation of 3.8% per annum (blended BCIS) on the live estimated portfolio from base epoch 30 April 2026. Completed, paused and cancelled schemes are excluded from the accrual. Both inputs are reproducible from the scheme table below, and the reconciliation panel shows the totals they derive from. Re-based 22 September 2026: the clock previously ran from a hand-selected subset of schemes that no longer reconciled with the published portfolio totals on this page.

Cost data: Announced costs are taken from original TfL Business Plans, GLA Budget papers, DfT/HS2 Ltd announcements and parliamentary statements. Current estimated costs are drawn from TfL Annual Reports, NAO reports, London Assembly Transport Committee papers, GLA Budget scrutiny documents, Mayor of London press releases, BBC London, and the Evening Standard.

Delay data: Weeks of delay calculated from original target completion date versus revised target or current date where no revised target exists. Where no completion date was formally set, delay is shown as — (not quantifiable).

2032 projection: The 2032 view uplifts each live scheme’s current estimated cost by compound construction inflation of 3.8% per annum over the six years from 2026, and leaves completed schemes at their outturn cost. It is computed from the scheme table, so it moves with the data rather than from a stored figure.

Primary sources: TfL Annual Reports & Business Plans · GLA Budget & London Assembly · National Audit Office · BBC London · GLA Capital Funding & Delivery Report Dec 2025 · NAO HS2 Update July 2024

ETI — recognised by infrastructure funders and development economists: The ETI framework mirrors the approach used by infrastructure funders, bond markets, and recognised development economists when assessing the productive value of public capital expenditure. Its components draw on HM Treasury Green Book benefit-cost ratio methodology, deprivation weighting consistent with Levelling Up Fund criteria, and network effect analysis aligned with WebTAG multi-modal appraisal guidance — the same analytical frameworks referenced by the Infrastructure and Projects Authority, development finance institutions, and institutional investors when evaluating public infrastructure programmes.

Disclaimer: This tracker is an independent professional accountability tool prepared by QUINTIN QS. It does not replicate, replace, or compete with any official government appraisal process. ETI scores and Stranded Value figures are derived from publicly available benchmark data and established appraisal frameworks — they are not the output of scheme-specific transport models such as TUBA or WebTAG-compliant multi-modal assessments. BCR inputs are drawn from published or analogous benchmarks, not bespoke modelling. Deprivation weighting is adapted from Levelling Up Fund criteria and is indicative in jurisdictions that use different deprivation indices. Delivery certainty scores reflect professional judgement applied consistently across all schemes. The methodology is fully disclosed, reproducible, and grounded in HM Treasury Green Book principles as updated in 2026 — but it carries the status of an independent analytical indicator, not a statutory appraisal. All figures are drawn from publicly available sources and are correct as of the date shown. If any government department holds more accurate data for a specific scheme, QUINTIN QS will update immediately upon notification. 🍓 If you believe any figure or fact shown here is incorrect, please write to mail@kevinbarryqs.com with the relevant scheme name, the correct figure, and a source reference — we will review and correct immediately if the evidence supports it. We are, after all, still human.

CPD Index — cost cap: The cost overrun % contribution to CPD-C is capped at 50 points — schemes with overruns above 100% score the maximum on this component. This prevents extreme outliers (e.g. schemes with 200%+ overruns) from distorting the index beyond its intended range.

CPD — about this acronym: CPD stands for Continued Prolonged Delays — a deliberate reference to Northern Ireland's Central Procurement Directorate, rebranded as Construction, Procurement, Delivery — the NI Executive body whose mandate is to ensure public infrastructure is built on time and on budget. The name is intentional.

Fewer promises.  Properly prepared projects.  Honest cost ranges.  Protected funding.  Named accountability. Build, reset or stop — never leave a project drifting indefinitely.